Question: For the activities described below: Determine the critical path, the expected time and vari- ance for each activity and along the critical path. Activity Optimistic
For the activities described below: Determine the critical path, the expected time and vari- ance for each activity and along the critical path.
Activity Optimistic Most likely Pessimistic Preceding task A123- B234- C456A
D 8 9 10 B E 2 5 8 C,D F456D G123E