Question: For the activity below, fill in the table. Comment on the status of the activity in terms of budget and schedule. Activity 1: 240 Footings

For the activity below, fill in the table.
For the activity below, fill in the table. Comment on the status of the activity in terms of budget and schedule. Activity 1: 240 Footings Duration: 3 months Start Date: 6 months from project start Total Cost: S2,400,000 Update Time: 7 months from project start Spent: $840,000 Footings Completed: 60 Footings formed, 24 Footings formed and reinforced 12 Footings formed, reinforced and poured Estimate ACWP BCWP BCWS To Complete At Completion Status Cost Variance Schedule Variance