Question: For the critical path method with three time estimates, what is the probability that a path with the mean duration of 15 days and the
For the critical path method with three time estimates, what is the probability that a path with the mean duration of 15 days and the standard deviation of 4 days can be completed within 19 days?
Cannot be determined
31%
23%
84%
69%