Question: For the following activities, please (a) write the critical path by letters and (b) calculate the earliest expected completion time. Activity Reference Letter Activity Duration
For the following activities, please
(a) write the critical path by letters and
(b) calculate the earliest expected completion time.
| Activity Reference Letter | Activity | Duration | Predecessor |
| A | Excavating | 5 days | - |
| B | Pouring Foundation | 10 days | A |
| C | Framing | 20 days | B |
| D | Roof | 10 days | C |
| E | Plumbing | 15 day | C |
| F | Electrical | 10 days | B |
| G | Masonry | 16 days | F |
| H | Interior | 10 days | F |
| I | Exterior | 5 days | D |
| J | Landscape | 4 days | I |