Question: For the following data, draw network. Find the critical path, slack time after calculating the earliest expected time and the latest allowable time Activity Duration

For the following data, draw network. Find the
For the following data, draw network. Find the critical path, slack time after calculating the earliest expected time and the latest allowable time Activity Duration Activity Duration (1-2) 5 (5-9) 3 (1-3) 8 (6 - 10) 5 ( 2-4) 6 (7-10) 4. (2-5) 4 (8 - 11) (2-6) (9-12) 2 (3-7) 5 (10 - 12) ( 3-8) 3 (11-13) 1 (4-9) 1 (12-13) 7 9 4. 4