Question: For the following project, 3 sections are expected every week. Each week is 5 working days with 8 hours a day. Using your answers to
For the following project, 3 sections are expected every week. Each week is 5 working days with 8 hours a day. Using your answers to previous questions, find the value of X1, X2, X3, X4, X5, X6, X7, X8, and X9?
Provide answers to three decimal places.

1 2 3 4 5 6 7 8 9 Actual Activity Manhours Men per Theoretical Activity Duration Time from start on Minimum per Unit gang Gang size Actual Gang size output for one unit first unit to start last rate buffer time A 100 4 X1 unit X3 X5 X7 B X9 350 6 X2 X4 X6 X8 X10 5