Question: For the following project: Activity Normal Time Crash Time Normal Cost Crash Cost Immediate (Weeks) (Weeks) Predecessor A 4 2,000 2, 100 B 2 2,200

 For the following project: Activity Normal Time Crash Time Normal Cost

For the following project: Activity Normal Time Crash Time Normal Cost Crash Cost Immediate (Weeks) (Weeks) Predecessor A 4 2,000 2, 100 B 2 2,200 2,800 C 500 500 D CO 6 2,300 2,600 A E 900 1,200 B IF 3 2 3,000 4,200 C G 4 2 1,400 2.000 D. E How long will the project take if crashed maximum

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!