Question: For the following project: Activity Normal Time Crash Time Normal Cost Crash Cost Immediate (Weeks) (Weeks) Predecessor A 4 2,000 2, 100 B 2 2,200

For the following project: Activity Normal Time Crash Time Normal Cost Crash Cost Immediate (Weeks) (Weeks) Predecessor A 4 2,000 2, 100 B 2 2,200 2,800 C 500 500 D CO 6 2,300 2,600 A E 900 1,200 B IF 3 2 3,000 4,200 C G 4 2 1,400 2.000 D. E How long will the project take if crashed maximum
Step by Step Solution
There are 3 Steps involved in it