Question: For the following project: Activity Predecessors Duration table [ [ A , None, 6 ] , [ B , None, 1 2 ] ,
For the following project:
Activity Predecessors Duration
tableANone,BNone,CADBEA BFA BGCHDIF GJHKHLD E JMD E I,NK
Draw an arrow diagram and calculate the earliest start time, earliest finish time, latest start time, latest finish time, free float and total float for each activity. Use the following applet to answer the question...,
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
