Question: For the following project: Activity Predecessors Duration table [ [ A , None, 6 ] , [ B , None, 1 2 ] ,

For the following project:
Activity Predecessors Duration
\table[[A,None,6],[B,None,12],[C,A,20],[D,B,17],[E,A, B,6],[F,A, B,13],[G,C,10],[H,D,6],[I,F, G,20],[J,H,8],[K,H,9],[L,D, E, J,5],[M,D, E, I,17],[N,K,8]]
Draw an arrow diagram and calculate the earliest start time, earliest finish time, latest start time, latest finish time, free float and total float for each activity. Use the following applet to answer the question...,
 For the following project: Activity Predecessors Duration \table[[A,None,6],[B,None,12],[C,A,20],[D,B,17],[E,A, B,6],[F,A, B,13],[G,C,10],[H,D,6],[I,F, G,20],[J,H,8],[K,H,9],[L,D,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!