Question: For the following project ( time in days ) , a ) Draw the PERT Network. b ) Determine the critical path and the completion

For the following project (time in days),
a) Draw the PERT Network.
b) Determine the critical path and the completion time.
c) Determine slack time for activities, A, C and E.
d) Find the probability to complete this project within 218days.
Activity
Immediate Predecessor
Optimistic Estimate
Most Likely Estimate
Pessimistic Estimate
A
-
30
50
70
B
-
80
90
100
C
-
85
100
115
D
A
19
25
31
E
B
91
100
115
F
G
D
E,F
52
12
55
15
58
18