Question: For the following questions, utilize the project data below. Assume all tasks start on the same day. (6 marks) TASKS AB takes 7 days TASK
- For the following questions, utilize the project data below. Assume all tasks start on the same day. (6 marks)
TASKS AB takes 7 days
TASK C takes 9 days
TASKS DEF takes 8 days
TASKS DGH takes 10 days
- What is the critical path for this project? (1mark)
- Define Slack Time? (i.e. Explain what it is) (2 mark)
- What is the slack time for C? (1 mark)
- What is the slack time for A? (1 mark)
What is the slack time for G?