Question: For the following table and report make earned value analysis to this project and represent the project situation (15 marks). Activity Predecessor duration Cost/day A

For the following table and report make earned value analysis to this project and represent the project situation (15 marks). Activity Predecessor duration Cost/day A None Total cost B 2 A 200 Actual compete% 100% Actual cost 400 B 300 D 3 900 400 B 300 100% 2 E 2 900 1100 D 100 33% 3 200 500 50 50% 150 100 0% 0 For the following table and report make earned value analysis to this project and represent the project situation (15 marks). Activity Predecessor duration Cost/day A None Total cost B 2 A 200 Actual compete% 100% Actual cost 400 B 300 D 3 900 400 B 300 100% 2 E 2 900 1100 D 100 33% 3 200 500 50 50% 150 100 0% 0
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
