Question: For the following table below given by Al Sahara Construction, do the following tasks: ACTIVITY DESCRIPTION PRDECESSORS Duration (Weeks) A Build internal components 2 B

  1. For the following table below given by Al Sahara Construction, do the following tasks:

ACTIVITY

DESCRIPTION PRDECESSORS

Duration

(Weeks)

A

Build internal components

2

B

Modify roof and floor

3

C

Construct collection stack

A

2

D

Pour concrete and install frame

A, B

4

E

Build high-temperature burner

C

4

F

Install pollution control system

C

3

G

Install air pollution device

D, E

5

H

Inspect and test

F, G

2

A] Draw a network path diagram (3 Marks)

B] Calculate Early Start, Early Finish, late Start, Late Finish for all tasks in the given table.

(10 Marks)

C] Identify the Critical Path in the diagram. (2 Marks)

3. Apply the Market Appraisal, Financial Appraisal, and Technical Appraisal with an industry project example on your own. (15 Marks)

4. A] Draw a neat Fishbone (i.e., Cause and Effect Diagram) diagram for the International Cargo Late Deliveries in the United Arab Emirates (UAE). (10 Marks)

Hint: Each cause should have minimum of four sub causes to earn full marks.

B] Analyse Ten (10) benefits of Fishbone Diagram in the Hypermarket Industry. (5 Marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!