Question: For the following table below given by Al Sahara Construction, do the following tasks: ACTIVITY DESCRIPTION PRDECESSORS Duration (Weeks) A Build internal components 2 B
- For the following table below given by Al Sahara Construction, do the following tasks:
| ACTIVITY | DESCRIPTION PRDECESSORS | Duration (Weeks) | |
| A | Build internal components | 2 | |
| B | Modify roof and floor | 3 | |
| C | Construct collection stack | A | 2 |
| D | Pour concrete and install frame | A, B | 4 |
| E | Build high-temperature burner | C | 4 |
| F | Install pollution control system | C | 3 |
| G | Install air pollution device | D, E | 5 |
| H | Inspect and test | F, G | 2 |
A] Draw a network path diagram (3 Marks)
B] Calculate Early Start, Early Finish, late Start, Late Finish for all tasks in the given table.
(10 Marks)
C] Identify the Critical Path in the diagram. (2 Marks)
3. Apply the Market Appraisal, Financial Appraisal, and Technical Appraisal with an industry project example on your own. (15 Marks)
4. A] Draw a neat Fishbone (i.e., Cause and Effect Diagram) diagram for the International Cargo Late Deliveries in the United Arab Emirates (UAE). (10 Marks)
Hint: Each cause should have minimum of four sub causes to earn full marks.
B] Analyse Ten (10) benefits of Fishbone Diagram in the Hypermarket Industry. (5 Marks)