Question: For the given PERT network, the three time estimates are given along the activity arrows in the figure. i . Determine the critical path, also
For the given PERT network, the three time estimates are given along the activity arrows in the figure.
i Determine the critical path, also determine the probability of completing the job in days.
ii What project duration will have confidence of completion.
The values of Z and corresponding probability are given in the following table:
tableProbability
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
