Question: For the given PERT network, the three time estimates are given along the activity arrows in the figure. i . Determine the critical path, also

For the given PERT network, the three time estimates are given along the activity arrows in the figure.
i. Determine the critical path, also determine the probability of completing the job in 20 days.
ii. What project duration will have 95% confidence of completion.
The values of Z and corresponding probability are given in the following table:
\table[[Z,1.0,1.1,1.2,1.5,2.0,3.0],[Probability,84.13,86.43,88.9,93.92,97.92,99.87]]