Question: For the given project, the earliest start ( ES ) and earliest finish ( EF ) are: ( Round your responses to two decimal places.

For the given project, the earliest start(ES) and earliest finish(EF) are:
(Round your responses to two decimal places.)
Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s)
A 478- G 51015 A, E
B 101112- H 111213 F
C 123- I 357 G
D 678 C J 141618 C
E 246 B, D K 3711 H, I
F 123 A, E