Question: For the given System Integration Project, the overall duration to complete the project is 14 days, and there are 5 activities as shown in the
For the given System Integration Project, the overall duration to complete the project is 14 days, and there are 5 activities as shown in the timeline The effort for each activity and cost per day is given. Also, the actual cost and actual % of work completed at the end of 9 days are given. what is the PV of the project at the end of 9 days? a. 16500 b. 10425 c. 10600 d. 10606