Question: For the MX project as described below, the PMO sent a note to the PM indicating that under the current plan, they would miss the

For the MX project as described below, the PMO sent a note to the PM indicating that under the
current plan, they would miss the project due date, so somehow they needed to accelerate the
timing for the project plan. The customer wanted the projected completed in 20 weeks and the
contract specifies a penalty of $5000 per week late up to 3 weeks and $10,000 per week late if
more than 3 weeks. Based on the project time and cost information shown in the table below,
what strategy should MX pursue?
Activity Predecessor Normal Time
(Weeks)
Crash Time
(Weeks)
Normal
Cost ($)
Crash
Cost ($)
Crash?
A None 4210,00015,000
B A 6530,00035,000
C A 218,00010,000
D B 4312,00018,000
E B, C 5320,00024,000
F D, E 7420,00029,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!