Question: For the MX project as described below, the PMO sent a note to the PM indicating that under the current plan, they would miss the
For the MX project as described below, the PMO sent a note to the PM indicating that under the
current plan, they would miss the project due date, so somehow they needed to accelerate the
timing for the project plan. The customer wanted the projected completed in weeks and the
contract specifies a penalty of $ per week late up to weeks and $ per week late if
more than weeks. Based on the project time and cost information shown in the table below,
what strategy should MX pursue?
Activity Predecessor Normal Time
Weeks
Crash Time
Weeks
Normal
Cost $
Crash
Cost $
Crash?
A None
B A
C A
D B
E B C
F D E
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
