Question: For the network below with all times indicating weeks, answer the following questions and justify your answers: a . What is the impact on the
For the network below with all times indicating weeks, answer the following questions and justify your
answers:
a What is the impact on the end date of the project if activity F slips by five weeks?
b What is the impact on the end date of the project if activity E slips by three weeks?
c What is the impact on activity H if activity B were to slip by four weeks?
d What is the impact on the end date of the project if activity D slips by four weeks?
Activity Preceding Activity
Time
Weeks
A
B
C A B
D B
E B
F C
G D
H D E
I F G H
Start A
B
C
D
E
End
F
G
H