Question: For the network diagram in class Do the forward pass and backward pass calculation and answer the following questions What is the duration of the
For the network diagram in class Do the forward pass and backward pass calculation and answer the following questions
What is the duration of the project?
What is the float of activity B?
What is the critical path? For example A-C-D-G -
, use this network diagram to
explain what critical path is
and how project managers use critical path in managing projects?