Question: For the network in problem 3 , determine the earliest and latest activity times and the slack for each activity. Indicate how the critical path


For the network in problem 3 , determine the earliest and latest activity times and the slack for each activity. Indicate how the critical path would be determined from this information. (5 points) Identify ALL the paths in the following network from start to activity 7, compute the length of each, and indicate the critical path. (10 points)