- For the network shown below, the project indirect cost for each day is $1,000. The following is the crashing information: 1. If you crash this project to reduce the total time by one day as long as the crashing cost is less than $1,000, which activity (activities) should you crash? A. Activity A B. Activity B C. Activity C D. Activity D E. Activity E