Question: For the next 4 questions consider the PERT/CPM network shown below. The baseline schedule for the project is an early start schedule. Currently, the project
For the next 4 questions consider the PERT/CPM network shown below. The baseline schedule for the project is an early start schedule. Currently, the project has been underway for 10 weeks. Assume that the budget for each activity is spent uniformly over the duration of the activity.
| Activity | Duration (weeks) | Personnel Req'd | BAC ($) | WS (person -weeks) | WP (person -weeks) | Work Remaining (person -weeks) | ACWP ($) |
| A | 8.0 | 3 | 36,000 | 24 | 24.0 | 0 | 32,000 |
| B | 4.0 | 4 | 24,000 | 16 | 16.0 | 0 | 24,000 |
| C | 5.0 | 4 | 30,000 | 4 | 0 | 20.0 | 0 |
| D | 10.0 | 2 | 30,000 | 12 | 8.0 | 12.0 | 16,000 |
| E | 10.0 | 5 | 75,000 | 30 | 35.0 | 15.0 | 50,000 |
| F | 6.0 | 3 | 27,000 | 0 | 0 | 18.0 | 0 |
| G | 9.0 | 6 | 81,000 | 0 | 0 | 54.0 | 0 |

Question 32) What is the BCWS of activity D?
a-) 15,000 b-) > 15,000 and 20,000 c-) > 20,000 and 25,000 d-) > 25,000 and 30,000 e-)> 30,000
Question 33) What is the BCWP of activity D?
a) 5,000 b)> 5,000 and 10,000 c)> 10,000 and 15,000 d) > 15,000 and 20,000 e)> 20,000
Question 34) What is the EACf (FAC) of activity D?
a) 25,000 b) > 25,000 and 30,000 c) > 30,000 and 35,000 d)> 35,000 and 40,000 e)> 40,000
Question 35) What is the SPI of activity D?
a) 0.50 b)> 0.50 and 1.00 c) > 1.00 and 1.50 d) > 1.50 and 2.00 e) > 2.00
F A Start D Finish B G EStep by Step Solution