Question: For the next 4 questions consider the PERT/CPM network shown below. The baseline schedule for the project is an early start schedule. Currently, the project

For the next 4 questions consider the PERT/CPM network shown below. The baseline schedule for the project is an early start schedule. Currently, the project has been underway for 10 weeks. Assume that the budget for each activity is spent uniformly over the duration of the activity.

Activity Duration (weeks) Personnel Req'd BAC ($) WS (person -weeks) WP (person -weeks) Work Remaining (person -weeks) ACWP ($)
A 8.0 3 36,000 24 24.0 0 32,000
B 4.0 4 24,000 16 16.0 0 24,000
C 5.0 4 30,000 4 0 20.0 0
D 10.0 2 30,000 12 8.0 12.0 16,000
E 10.0 5 75,000 30 35.0 15.0 50,000
F 6.0 3 27,000 0 0 18.0 0
G 9.0 6 81,000 0 0 54.0 0

For the next 4 questions consider the PERT/CPM

Question 32) What is the BCWS of activity D?

a-) 15,000 b-) > 15,000 and 20,000 c-) > 20,000 and 25,000 d-) > 25,000 and 30,000 e-)> 30,000

Question 33) What is the BCWP of activity D?

a) 5,000 b)> 5,000 and 10,000 c)> 10,000 and 15,000 d) > 15,000 and 20,000 e)> 20,000

Question 34) What is the EACf (FAC) of activity D?

a) 25,000 b) > 25,000 and 30,000 c) > 30,000 and 35,000 d)> 35,000 and 40,000 e)> 40,000

Question 35) What is the SPI of activity D?

a) 0.50 b)> 0.50 and 1.00 c) > 1.00 and 1.50 d) > 1.50 and 2.00 e) > 2.00

F A Start D Finish B G E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!