Question: For the next eight questions, consider the following data for a project to install new gym equipment at the S&L campus: Activity Time Immediate Activity

For the next eight questions, consider the
For the next eight questions, consider the following data for a project to install new gym equipment at the S&L campus: Activity Time Immediate Activity (days) Predecessor(s) A 2 4 4 D 2 E 6 B F 00 C D G 3 E 5 C, E F,G,H - 4 If Task C took 2 extra days to complete, the length of the project increased by how many days? (Assume Task C started at ES i.e. earliest start) Select one: O a. None of the above Ob. 3 O c. O d. 1 O e. 2 Clear mu