Question: For the Office Table above (the first MRP table), what is the Projected On-Hand Inventory in the week of 9/19? For the Office Table above,

For the Office Table above (the first MRP table), what is the Projected On-Hand Inventory in the week of 9/19?
For the Office Table above, what are the Planned Order Receipts in the week of 8/8?
For the Table-Top Assembly above, what are the Net Requirements in the week of 9/19?
For the Table-Top Assembly above, what are the Planned Order Releases in the week of 9/5?
Bill of Material for Office Table Table Final Assembly Top Assembly (1 required) Support Assembly (1 required) Bracket (6 required) Wood Screw (48 required) Center Support (1 required) Side Support (2 required) MS.53 An office furniture manufacturer needs to calculate material requirements for one of its most popular tables. The graphic above shows the bill of material for this item. Below are the MRP tables for the top-level assembly (the Office Table Final Assembly) and one of its sub-assemblies (the Table-Top Assembly): 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 500 200 500 800 400 200 380 Office Table Final Assembly Gross Requirements Scheduled Receipts Projected On-Hand Inv. Net Requirements Planned Order Receipts Planned Order Releases Lead Time (in weeks) Lot Size 125 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 150 110 Table-Top Assembly Gross Requirements Scheduled Receipts Projected On-Hand Inv. Net Requirements Planned Order Receipts Planned Order Releases Lead Time (in weeks) ILot Size 1 20Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts