Question: For the orginal manufacturing process found below, balance the process by time using only 4 operations . For the Time - Balanced 4 Step Process,
For the orginal manufacturing process found below, balance the process by time using only
operations For the Time
Balanced
Step Process, the Operation Number order is not important. seek timebalances step process
Original Process
Operation Number Operator Operator Cycle Time
Seconds
PCT