Question: For the parallel production process shown above, R 1 = 0 . 9 5 , R 2 = 0 . 8 5 , R 3

For the parallel production process shown above, R1=0.95,R2=0.85,R3=0.98.
For the given parallel production process, the reliability =,%(enter your response as a percentage rounded to two decimal places).
For the parallel production process shown above,