Question: For the parallel production process shown above, Ry = 0 . 9 4 , R 2 = 0 . 8 8 , R 3 =

For the parallel production process shown above, Ry =0.94, R2=0.88, R3=0.96.For the given parallel production process, the reliability = decimal places).%(enter your response as a percentage rounded to two