Question: For the preceding project in EACH activity determine: a. the slack b. earliest finish c. latest finish d. project duration Activity Predecessors Durations (days) A

For the preceding project in EACH activity determine:
a. the slack b. earliest finish c. latest finish
d. project duration
Activity Predecessors Durations (days) A none 2 B A 3 C A 4 D B 1 E B and C 3 F D and E 6 G C and D 3Step by Step Solution