Question: For the project below: Activity Predecessor Normal Duration ( days ) Shortest Duration ( days ) crash cost - normal cost ( $ 0 0
For the project below: Activity Predecessor Normal Duration days Shortest Duration days crash costnormal cost $s none NA NA NA
a Construct a CPM network representation with ES EF LS and LF Times for the project. b What is the critical path, and how long will the project take to complete? c What activity or activities should you crash to reduce the duration of the project by one day? What will be the increase in the project cost?