Question: For the project below, develop the node network and perform the CPM calculations. Then, calculate the normal, least - cost , and crash duration for

For the project below, develop the node network and perform the CPM calculations. Then, calculate the normal, least-cost, and crash duration for the project. Calculate the cost associated with each duration and graphically show the crashing. Indirect cost (overhead) is $200 per day.
\table[[Activity,IPA,Duration,Cost $],[Normal,Crash,Normal,Crash],[A,1,1,$800,$800],[B,A,7,4,$1,000,$1,600],[C,A,6,4,$300,$500],[D,A,3,2,$400,$800],[E,B,3,1,$100,$200],[F,B,C,7,5,$500,$800],[G,D,8,4,$1,200,$1,400],[H,E,7,6,$350,$600],[I,F,5,3,$700,$850],[J,F,G,3,2,$500,$1,000],[K,H,I,J,5,4,$450,$800]]
For the project below, develop the node network

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!