Question: For the project below, please find out: begin { tabular } { | c | c | c | } hline Activity &

For the project below, please find out:
\begin{tabular}{|c|c|c|}
\hline Activity & Precedes & Time (wk.)\\
\hline Start & A, B & -\\
\hline A & C, D & 6\\
\hline B & G & 4\\
\hline C & E & 4\\
\hline D & F & 5\\
\hline E & H & 6\\
\hline F & H & 6\\
\hline G & I & 8\\
\hline H & End & 5\\
\hline I & End & 6\\
\hline
\end{tabular}
1. Draw the diagram
2. EST, ECT, LST, and LCT for each activity
3. Slack time for each activity
4. Identify the critical path
5. What is the duration for this project?