Question: For the project described by the table below, what is the late finish time for activity D ? Assume that, for each activity, the finish
For the project described by the table below, what is the late finish time for activity D? Assume that, for each activity, the finish time must equal to start time plus expected duration.
| Activity | Immediate Predecessors (constraint type, lag) | Expected Duration |
| A | --- | 3 |
| B | A(fts,1) | 4 |
| C | A(stf,5) | 5 |
| D | A(sts,3) | 6 |
| E | D(ftf,0) | 2 |
| F | C(fts,2) | 1 |
| G | E(fts,1), F(ftf,2) | 5 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts