Question: For the project described by the table below, what is the late finish time for activity D ? Assume that, for each activity, the finish

For the project described by the table below, what is the late finish time for activity D? Assume that, for each activity, the finish time must equal to start time plus expected duration.

Activity

Immediate Predecessors (constraint type, lag)

Expected Duration

A

---

3

B

A(fts,1)

4

C

A(stf,5)

5

D

A(sts,3)

6

E

D(ftf,0)

2

F

C(fts,2)

1

G

E(fts,1), F(ftf,2)

5

Step by Step Solution