Question: For the project schedule below Activity Cost Month Month Month Month Month Month 1 2 3 4 5 6 A $500 B $1200 C $800
For the project schedule below
| Activity | Cost | Month | Month | Month | Month | Month | Month |
|
|
|
| 1 | 2 | 3 | 4 | 5 | 6 |
|
|
| ||
| A | $500 |
|
|
|
|
|
|
|
|
|
| B | $1200 |
|
|
|
|
|
|
|
|
|
| C | $800 |
|
|
|
|
|
|
|
|
|
| D | $2000 |
|
|
|
|
|
|
|
|
|
| E | $1200 |
|
|
|
|
|
|
|
|
|
| F | $3000 |
|
|
|
|
|
|
|
|
|
| G | $600 |
|
|
|
|
|
|
|
|
|
| H | $700 |
|
|
|
|
|
|
|
|
|
| I | $500 |
|
|
|
|
|
|
|
|
|
| J | $600 |
|
|
|
|
|
|
|
|
|
After three months on the job, the contractor concluded that Activities A, B, and D are completed, 20% of Activity F was completed, 80% of Activity C was completed, and 40% of Activity E was completed. The project has cost the contractor a total of $5350. For this project,
- Calculate the overall percent complete for the project.
- Using earned value concepts determine the ACWP, BCWP, BCWS, CV, SV, SV(days), CPI, SPI, FCV, FSV
- Based on performance so far, do you believe the subcontractor will finish the job on time? Within budget? Justify your answer.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
