Question: For the project shown in the following table, LOADING... , calculate the internal rate of return (IRR) . Then indicate, for the project, the maximum
For the project shown in the following table,
LOADING...
,
calculate the internal rate of return
(IRR).
Then indicate, for the project, the maximum cost of capital that the firm could have and still find the IRR acceptable.
Question content area bottom
Part 1
The project's IRR is
enter your response here
Initial investment
(CF0)
$100,000
Year
(t)
Cash inflows
(CFt)
1
$10,000
2
$15,000
3
$30,000
4
$40,000
5
$45,000