Question: For the project tasks given in the table below, draw the network diagram and use it to find the critical chain and the critical path.

For the project tasks given in the table below, draw the network diagram and use it to find the critical chain and the critical path. Use this information to answer the questions below. Task Duration Predecessors Resource A 3 Ginger B N A Brooke C A Ginger D A Ginger F C. D Brooke F Priyanka E Prinanka H G Ginger