Question: For the question below, exactly two answers are correct. If you tick more than two, you will earn zero marks. Activities X , Y ,
For the question below, exactly two answers are correct. If you tick more than two, you will earn zero marks.
Activities X Y and Z are project tasks having precedence relations as shown. The estimated durations are in parentheses. If X starts at time T what will be the finish time for activity Z
a
Zs finish time will be T plus sum of actual durations of Y and Z
b
Zs finish time is decided by the maximum of actual duration X and Y
c
Zs finish time is unaffected by the actual completion of X
d
Zs finish time will be TTxTz
e
Zs finish time depends on the realtime interplay between X and Y
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
