For the question below, exactly two answers are correct. If you tick more than two, you will earn zero marks.
Activities X, Y, and Z are project tasks having precedence relations as shown. The estimated durations are in parentheses. If X starts at time T, what will be the finish time for activity Z?
a.
Zs finish time will be T+5 plus sum of actual durations of Y and Z
b.
Zs finish time is decided by the maximum of actual duration X and Y
c.
Zs finish time is unaffected by the actual completion of X
d.
Zs finish time will be T+Tx+Tz
e.
Zs finish time depends on the real-time interplay between X and Y

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!