Question: For the same actual demand data above, perform a forecast using: Moving average of 3 periods. Exponential smoothing of (a=0.2).Make the first forecast value equal

For the same actual demand data above, perform a forecast using:

Moving average of 3 periods.

Exponential smoothing of (a=0.2).Make the first forecast value equal to 3.

Sketch your results on an excel sheet (period vs. Demand and vs. forecast values)

Date Actual demand (TVs/day) Forecast value (TVs/day) Moving average (3) expo smoothing (a=0.2) 1 7-Sep-14 0 3 2 8-Sept. 2 5 3 9-Sept. 6 7 4 10-Sept. 15 12 5 11-Sept. 8 10 6 12-Sept. 7 8 7 13-Sept. 7 4 8 14-Sept. 2 0