Question: For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = hours (enter

For the schedule developed using Johnson's rule,

For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = hours (enter your response as a whole number).

Using Johnson's rule for 2-machine scheduling, the sequence is: Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Scheduled Order Job 1 Operation 1 (hours) 1 Job A B D E F 10 8 11 4 2 Operation 2 (hours) 3 12 7 9 6 13

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!