Question: For the situation below, name the most appropriate contract type. Time is of essence and you need work to begin ASAP Question 1 options: Time
For the situation below, name the most appropriate contract type.
"Time is of essence and you need work to begin ASAP"
Question 1 options:
|
| Time & Material |
|
| CP |
|
| CPIF |
|
| None of the choices |
|
| PO |
Question 2 (3 points)
For the situation below, name the most appropriate contract type.
You need to buy a standard laser printer.
Question 2 options:
|
| None of the choices |
|
| FPIF |
|
| CPIF |
|
| PO |
|
| CPAF |
Question 3 (3 points)
For the situation below, name the most appropriate contract type.
"You have a detailed scope of work but the economic conditions are not
stable."
Question 3 options:
|
| None of the choices |
|
| Time & Material |
|
| PO |
|
| FPEPA |
|
| CPIF |
Question 4 (5 points)
The supplier delivers an incentive fee project at an actual cost of $90000. The terms of the
contract are a target cost of $100000, a target fee of $10000, and therefore a target price of
$110000. The over-run/under-run share ratio is 70% to the customer and 30% to the supplier.
The final price is:
Question 4 options:
|
| $13000 |
|
| 103000 |
|
| $93000 |
|
| 113000 |