Question: For the table below , JOB # PROCESSING TIME (Hrs) DUE DATE (Hrs) 1 12 15 2 6 24 3 14 20 4 3 8

For the table below ,

JOB #

PROCESSING TIME (Hrs)

DUE DATE (Hrs)

1

12

15

2

6

24

3

14

20

4

3

8

5

7

6

Determine the sequence for :

a.(i) EDD, (ii) SPT schedules and for each calculate

b.Makespan

c.Average flow time.

d.Average or mean tardiness.

N/b: Topic-Planning and Scheduling under production management