Question: For the typical project presented in Table 1 , the owner of the company asks you the following questions that you need to answer: Question
For the typical project presented in Table the owner of the company asks you the following questions that you need to answer:
Question : What delivery time duration should we promise to the customer if we need to be sure that we will deliver on time?
Question : Winter commences in days and you prefer that all outdoors activities have finished. What is the probability that roof tiling will be completed by the end of the day
Question : If the construction manager had promised to the customer the delivery date indicated by the outcome of question what would be the probability of delivering late?