Question: For this assignment, you will start by calculating forward pass for this schedule based on the given information that the early start for activity A

For this assignment, you will start by calculating forward pass for this schedule based on the given information that the early start for activity A is day 1. Once you have completed the forward pass, you will calculate a backward pass based on the given information that the late finish of activity D is day 22. Upon finishing the backwards pass, you will then calculate total float for each activity. S