For this project, the constraint is that you only have 3 engineers available per day. Answer the
Fantastic news! We've Found the answer you've been seeking!
Question:
For this project, the constraint is that you only have 3 engineers available per day. Answer the 2 questions with Yes or No in the space provided. According to the diagram, is it possible to schedule Activity 1 and 2 on Day 1? According to the diagram, is it possible to schedule Activities 1, 2 and 3 on Day 2? Phrase your answers like this: A = ______ B = ______ Explain your answer.