Question: For this project you will complete a bid for a Real Estate Office ( see plans on Moodle ) . You will complete this estimate

For this project you will complete a bid for a Real Estate Office (see plans on Moodle). You will
complete this estimate two different ways.
First, complete a rough estimate based on sf pricing provided in RS Means data book for this
office to be built in Charlotte, NC.
Secondly, you are to complete a full quantity takeoff with pricing and subcontractor bids
(provided).
Prepare a complete Quantity Takeoff for the related work on the Real Estate Office.
Cost of General Conditions
Material List for Rebar
Material List for Concrete
Material List for Lumber
Labor Cost for installation of wood doors with trim and hardware using a labor rate of
$28.00/hr which includes all burden.
Labor Cost for installation of toilets and bath accessories using a labor rate of $28.00/hr
which includes all burden.
Subcontractors bidding list is attached as well. Please note this is due by May 8th at 11:59 and
there will be no late submissions allowed.
The following material bids will be supplied:
Rebar
Concrete
Lumber
Wood Doors
Toilet & Bath Accessories
The following subcontractor bids will be supplied:
Concrete Labor (no materials)
Masonry
Framing Labor (no materials)
Insulation
Siding and rain gutters
Roofing
Storefronts & Windows
Drywall
Ceramic Tile
Acoustical Ceilings
Flooring
Paint
Plumbing
HVAC
Electrical
Building Excavation
Provide a final summary tabulation on a simple Excel spreadsheet see below for example.
Turn in your summary tabulation and your detailed quantity take-off calculations.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!