Question: For this question, please use the standard normal distribution table, Table A2. It has been estimated that the mean time required to complete a project

For this question, please use the standard normal distribution table, Table A2. It has been estimated that the mean time required to complete a project is 20 weeks and the variance of project completion time is 9 weeks. So there is a 95% chance that the project can be completed in
| 10 weeks. | ||
| 19 weeks. | ||
| 20 weeks. | ||
| 26 weeks. |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts