Question: For this question, use the following example for an MTS environment. Note that ATP is discrete and the MPS receipt scheduled in period 1 was

For this question, use the following example for an MTS environment. Note that ATP is discrete and the MPS receipt scheduled in period 1 was carried over from a previous plan. On hand: 15 Planning time fence: 7 Lot size: 40 Safety stock: 8 Demand time fence: 2Period12345678Forecast2020202020202020Actual Orders1815271010865PAB15MPS Receipts40ATPGiven the above information and using