Question: For this schedule use PERT to find the completion time for the activities but also find the probability of completing the project in 15,16,17,18 months

For this schedule use PERT to find the completion time for the activities but also find the probability of completing the project in 15,16,17,18 months
Most likely Max duration Predecessors Activity Min duration A Requirements analysis 2 months B Programming 6 months C Hardware acquisition 3 months D Train users 12 months E Implementation 3 months F Testing 1 month 3 months 7 months 3 months 12 months 5 months 1 month 4 months 9 months 3 months 12 months 7 months 2 months None A A A B, C EStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock