Question: For this week's assignment there are three problems to ponder. Please prepare your response to the questions as an Excel spreadsheet and submit it below.

For this week's assignment there are three problems to ponder. Please prepare your response to the questions as an Excel spreadsheet and submit it below. You will be graded on your answers and your process. This assignment is worth 100 points total.
Problem 1- Quantitative Risk Assessment (30 points)
Assume the following information:
Probability of Failure Consequences of Failure
Maturity =.3 Cost =.1
Complexity =.3 Schedule =.7
Dependency =.5 Performance =.5
Calculate the Overall risk factor for this project. Would you assess this level of risk as low, moderate, or high? Why?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!