Question: For your final assignment, you will create a 10- to 15-page project management plan from the perspective of the project manager of the Denver, CO,
For your final assignment, you will create a 10- to 15-page project management plan from the perspective of the project manager of the Denver, CO, VA hospital using the components that you have drafted throughout this course. Finetune these components and ensure your project management plan includes the following elements:
1. At the 20 percent point of completion for the Denver, CO, Veterans Administration (VA) hospital project with total budgeted funds of $2,000,000, the total costs to date for the project are $600,000. Given the following information, determine:
- Earned value
- Schedule performance index (SPI)
- Cost performance index (CPI)
- Forecasted range of final project results
Based on the risk thresholds in Hillson and Simon (2020, Figure 4-8), determine where the cost and performance factors of this project are using the example probability-impact scales. Include a probability-impact scale table.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts