Question: Formulas: Critical Ratio for each job = CR = ( Due Date Days ) / ( Processing Time Days ) Average completion time = (
Formulas:
Critical Ratio for each job CR Due Date DaysProcessing Time Days
Average completion time Sum of all flow timestotal no of jobs
Percentage Utilization Sum of all processing timesSum of all flow times
Average no of jobs in the system Sum of all flow timesSum of all processing times
Average lateness Sum of all late timeTotal no of jobs
Thus, the appropriate job sequencing based on the above data and the appropriate sequencing rule is given as in the below sheet, along with the calculations for average tardiness, average no of jobs, average flow time. no of late jobs, maximum lateness, the ratio of average flow time to average no of jobs, and the optimal job sequence itself.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock