Question: Formulas: Critical Ratio for each job = CR = ( Due Date Days ) / ( Processing Time Days ) Average completion time = (

Formulas:
Critical Ratio for each job = CR =(Due Date Days)/(Processing Time Days)
Average completion time =(Sum of all flow times)/(total no. of jobs)
Percentage Utilization =(Sum of all processing times)/(Sum of all flow times)
Average no. of jobs in the system =(Sum of all flow times)/(Sum of all processing times)
Average lateness =(Sum of all late time)/(Total no. of jobs)
Thus, the appropriate job sequencing based on the above data and the appropriate sequencing rule is given as in the below sheet, along with the calculations for average tardiness, average no. of jobs, average flow time. no. of late jobs, maximum lateness, the ratio of average flow time to average no. of jobs, and the optimal job sequence itself.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!