Question: Formulas Line balancing Available Time = Net time available excluding meeting time, lunch break etc... Cycle Time = A v a l i a b

Formulas
Line balancing
Available Time = Net time available excluding meeting time, lunch break etc...
Cycle Time =AvaliableTimeUnitsRequired
Theoretical minimum number of workstations =??TaskTimeCycleTime
To measure the effectiveness, we have to find the efficiency and idle time by
using the following formulas:
Efficiency =??TaskTimeActualnumberofworkstationslargestassignedcycletime100
Idle Time Actual number of workstations x largest assigned cycle time Question 5. A company is designing a product layout for a new product. It
plans to use this production line eight hours a day in order to meet a schedule of
400 units per day. The tasks necessary to produce this product are detailed in the
table below.
a. What is the required cycle time?
b. What is the theoretical minimum number of workstations needed to meet the
schedule?
c. Use the longest task time approach to balance the assembly line
d. What is the idle time?
e. What is the efficiency?
f. Does the solution have the minimum number of stations?
Formulas Line balancing Available Time = Net time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!